BSOP 429 Final Exam 100% Correct Answers

BSOP 429 Final Exam 100% Correct Answers for 45 Only

teacher asking a question to the class

BSOP 429 Week 8 Final Exam 

  1. (TCO 4) The priority rule, which will sequence jobs in the order they are received, is _____. (Points : 5)
  2. (TCO 2) In an assignment method problem, if it takes Abe 3 hours to build a birdhouse and 4 hours for a doghouse, and Betty takes 4 hours for a birdhouse and 3 hours for a doghouse, what is the reduced cost (in hours) of assigning Betty to build the doghouse? (Points : 5)
  3. (TCO 2) A major difference between manufacturing and service systems in terms of scheduling is (Points : 5)
  4. (TCO 3) Scheduling in service systems may involve scheduling which of the following?
  5. (Points : 5)
  6. (TCO 5) The owner and operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:
  7. (TCO 6) Building up an inventory of standard parts or modules instead of immediately producing the finished end items is the essence of (Points : 5)
  8. (TCO 7) With regard to suppliers, JIT systems typically require (Points : 5)
  9. (TCO 10) Which of the following is characteristic of the JIT philosophy? (Points : 5)
  10. (TCO 1) In make-to-stock systems, fluctuations in sales volume are managed through which of the following? (Points : 5)
  11. (TCO 5) In an MRP master schedule, the planning horizon is often separated into a series of times periods called (Points : 5)

BSOP 429 Midterm Exam 1

BSOP 429 Midterm Exam 1

Page 1

1. (TCO 12) _____ is the objective under JIT and time-based competition.
2. (TCO 2) Which of the following lead-time elements can be compressed into one well-designed PAC system?
3. (TCO 3) What happens to inventory as the number of kanban cards increases?
4. (TCO 1) In managing supplier relations, which of the following is a beneficial setup?
5. (TCO 6) When linking marketing requirements and manufacturing strategy, what design approaches for shop floor system should be considered?
6. (TCO 9) Which of the following is true?
7. (TCO 4) According to Elyahu Goldratt, the TOC system uses a scheduling approach called _____.
8. (TCO 5) The amount of time covered by the basic MRP record is called the _____.