Industrial Building, Inc., has two project teams installing virtually identical, four-story commercial buildings for a customer in two separate cities. Both projects have a planned daily cost of 100 and a planned daily earned value of 100. The first 6 days for each team have progressed as follows. Compare the two projects in terms of general progress and according to critical ratios.

DayTeam A:Earned ValueTeam B:Earned ValueA:CostB:Cost
190909595
292889894
39495101102
498101106109
51048911699
6112105126118

Compare the two projects in terms of general progress and according to critical ratios.

Price of Answer: Just US$4 only (Instant Download)

Buy Now

Need Assistance…??  email us at [email protected].

If you need any type of help regarding Homework, Assignments, Projects, Case study, Essay writing or anything else then just email us at [email protected]solvemyquestion.com.  We will get back to you ASAP. Do not forget to maintain the time frame you need your work to be done.